dc.identifier.citationPaulino Gómez, M. M., Pérez Brioso, M. E. (2019). Indemnización por servidumbre de paso de líneas de transmisión eléctrica. caso: ETED, Abril-Mayo 2019 (Tesis de maestría). Recuperdo dees_ES
dc.identifier.urihttps://repositorio.unphu.edu.do/handle/123456789/2142
dc.description.abstractEl presente estudio analiza cómo la Empresa de Transmisión Eléctrica Dominicana (ETED) desarrolla el proceso de negociación para otorgar las indemnizaciones por servidumbre de paso de líneas de transmisión eléctrica. La metodología utilizada condujo a la identificación, análisis y selección de las leyes que regulan las empresas del sector eléctrico nacional, así como las normativas internas de la empresa objeto de estudio. Para la recogida de datos se aplicó un cuestionario al personal de alta gerencia y mandos medios de la ETED. Los instrumentos de recopilación de información se aplicaron durante dos meses durante los cuales se revisaron los archivos de la empresa ETED para establecer los criterios utilizados para indemnizar los propietarios de los predios, por la servidumbre de transmisión eléctrica, en 155 municipios ubicados a nivel nacional. Los resultados revelan la necesidad de revisar los procesos de indemnización para la gestión de proyectos eléctricos, lo que conllevó la presentación de una propuesta metodológica para el cálculo de indemnizaciones justas y equitativas para los afectados por la constitución de servidumbres. Se recomienda capacitar continuamente y dar mayor participación a los agentes fiscalizadores en los procesos de indemnización a las personas afectadas. This study analyzes how the Dominican Electricity Transmission Company (ETED) develops the negotiation process to grant compensation for the easement of the passage of electric transmission lines. The methodology used led to the identification, analysis and selection of the laws that regulate the companies of the national electricity sector, as well as the internal regulations of the company under study. For the collection of data, a questionnaire was applied to the senior management and middle managers of the ETED. The information collection instruments were applied for two months during which the archives of the ETED company were reviewed to establish the criteria used to compensate the owners of the properties, for the servitude of electric transmission, in 155 municipalities located nationwide. The results reveal the need to review the compensation processes for the management of electrical projects, which led to the presentation of a methodological proposal for the calculation of fair and equitable compensation for those affected by the constitution of easements. It is recommended to continually train and give greater participation to the supervisory agents in the compensation processes to the affected persons.es_ES
dc.description.abstractThis study analyzes how the Dominican Electricity Transmission Company (ETED) develops the negotiation process to grant compensation for the easement of the passage of electric transmission lines. The methodology used led to the identification, analysis and selection of the laws that regulate the companies of the national electricity sector, as well as the internal regulations of the company under study. For the collection of data, a questionnaire was applied to the senior management and middle managers of the ETED. The information collection instruments were applied for two months during which the archives of the ETED company were reviewed to establish the criteria used to compensate the owners of the properties, for the servitude of electric transmission, in 155 municipalities located nationwide. The results reveal the need to review the compensation processes for the management of electrical projects, which led to the presentation of a methodological proposal for the calculation of fair and equitable compensation for those affected by the constitution of easements. It is recommended to continually train and give greater participation to the supervisory agents in the compensation processes to the affected persons.
dc.language.isoeses_ES
dc.publisherSanto Domingo: Universidad Nacional Pedro Henríquez Ureñaes_ES
dc.rightsAttribution-NonCommercial-NoDerivatives 4.0 Internacional*
dc.rights.urihttp://creativecommons.org/licenses/by-nc-nd/4.0/*
dc.subjectEmpresa de Transmisión Eléctrica Dominicanaes_ES
dc.subjectServicios de electricidades_ES
dc.titleIndemnización por servidumbre de paso de líneas de transmisión eléctrica. caso: ETED, Abril-Mayo 2019es_ES
dc.typeThesises_ES


Ficheros en el ítem

Thumbnail
Thumbnail

Este ítem aparece en la(s) siguiente(s) colección(ones)

Mostrar el registro sencillo del ítem

Attribution-NonCommercial-NoDerivatives 4.0 Internacional
Excepto si se señala otra cosa, la licencia del ítem se describe como Attribution-NonCommercial-NoDerivatives 4.0 Internacional